Wednesday, January 14, 2015

Malibu approves sewage treatment plant

http://www.latimes.com/local/westside/la-me-0114-malibu-sewer-20150114-story.html

By MARTHA GROVES JANUARY 13, 2015, 9:03 PM

Taking a long-anticipated step to reduce coastal pollution, the Malibu City Council has voted to approve construction of a wastewater treatment plant in the Civic Center area.

The project's roughly $40-million first phase, which is expected to be operating by June 2017, would provide sewage treatment for nearly 50 property owners, including the city itself. Others include the Los Angeles County public library and fire station, the Malibu Colony Plaza shopping center and the Malibu Country Mart.

"We commend the City Council for taking this important step to improve the water quality in Malibu Lagoon and the Malibu groundwater basin," said Samuel Unger, executive director of the Los Angeles Regional Water Quality Control Board.

Water quality officials have long criticized Malibu for what they perceived to be its slow pace of addressing water pollution in Malibu Creek, Malibu Lagoon and Surfrider Beach. In 2009, the water board approved a prohibition on septic systems in the city's core.

Most commercial and residential properties in Malibu use septic systems. The agency said pollutants leaching from aging, overtaxed systems caused much of the ongoing water quality problems.

City Manager Jim Thorsen said Malibu would seek a low-interest state loan, to be guaranteed by the affected property owners, and form an assessment district to cover the costs of building and operating the plant. If the district is approved, property owners would be assessed amounts ranging from $4,000 a year to as much as $500,000 a year.

The membrane bioreactor plant would be located just north of Pacific Coast Highway along Civic Center Way, according to a map on the city's website. The plant would initially be capable of treating about 190,000 gallons a day to a level that would allow the water to be reused in Legacy Park, the city's highly praised storm water treatment zone, and elsewhere.

The second phase, which would begin to incorporate some residential properties, would bring the level to 360,000 gallons. The regional water board has said that phase must be online by late 2022. A third phase would raise the total to 500,000 gallons a day in 2025.

Dozens of people spoke for and against the project at the council meeting Monday night. Many residents have expressed concern that installing sewers would unleash a wave of development. The five council members voted unanimously to approve the environmental impact report just before 11 p.m.

"It was the outcome we hoped for," said Sarah Sikich, vice president of Heal the Bay, an environmental advocacy group.

The project is expected to get other necessary approvals and permits in coming months from the regional water board and the California Coastal Commission.

"This is a landmark step," Sikich said, "to move from local permitting to state permitting and from concept to implementation."

martha.groves@latimes.com
Twitter: @MarthaGroves

Copyright © 2015, Los Angeles Times

Friday, January 9, 2015

Could O.C. get drinking water from the sea? Huntington Beach desalination plant gets a boost

2015-01-09 00:09:03

The Orange County Water District, which manages the groundwater basin in north and central county, gave a much-needed boost this week to a proposed desalination plant in Huntington Beach by agreeing to purchase its water.

At nearly $2,000 per acre-foot, desalinated water costs about twice as much as water imported from Northern California. Until this week, the steep price tag for what Poseidon Water calls a drought-proof water supply has failed to attract water agencies.

But Wednesday night, the Orange County Water District, which sells water to local retail agencies, said it was interested in buying all of the 56,000 acre-feet of drinking water the plant would produce.

The negotiations come after 15 years of planning, but before Poseidon has lined up all the permits necessary to actually break ground on the facility. Poseidon needs one more permit from the California Coastal Commission and must complete a multiphase technical study to get it.

Additionally, it’s not certain whether Poseidon will have to re-apply for its other permits once the state releases new rules governing desalination operations statewide in the fall.

“It doesn’t look like the way this thing is designed will comply with those standards,” said Joe Geever, an environmental consultant for Surfrider Foundation and expert on coastal permitting. “You’re talking about a contract for a project that is speculative at best.”

Poseidon, however, heralded the contract negotiations as a critical step in securing a drought-proof water supply for Orange County. The contract may come back for a final vote as soon as March.

“We look forward to these formal discussions with OCWD,” Poseidon Vice President Scott Maloni said.

The contract between OCWD and Poseidon would govern how much OCWD would pay for the desalinated water and who would foot the bill for the likely changes that are projected to cost $892 million.

Poseidon struck a similar deal with the San Diego County Water Authority for the 48,000 acre-feet of water it expects to produce per year at its Carlsbad desalination facility late this year.

A deal with OCWD would be a coup for Poseidon, which has had trouble finding buyers for the desalinated water, according to Irvine Ranch Water District General Manager Paul Cook.

Years of negotiations between Poseidon and the Municipal Water District of Orange County – a water wholesaler – and its member agencies fell through about 18 months ago.

“The Poseidon guys said, ‘This isn’t going to work. We need to find a buyer.’ And then they started working with OCWD,” Cook said.

So far, OCWD has turned out to be friendlier partner. Nine of the 10 OCWD board members voted Wednesday to advance the negotiations for Poseidon’s desalinated water.

Cook said he worries about the uncalculated costs of the Poseidon project, as well as price hikes – costs he expects would be passed on to customers. He said his agency doesn’t need the extra water, and he doesn’t believe his customers should have to pay extra.

Cook also questioned whether the OCWD has legal authority to act as the middleman between Poseidon and the retail water agencies.

“There’s a lot more questions that go along with it, and not least of all: Who really wants this water?” Cook said. “We’re not interested in paying for a project we don’t derive any benefit from.”

The water will shore up the groundwater basin, OCWD General Manager Mike Markus said.

Contact the writer: aorlowski@ocregister.com

Tuesday, December 30, 2014

City of Malibu publishes CCWTF EIR edits

http://www.malibusurfsidenews.com/city/city-publishes-ccwtf-eir-edits

City publishes CCWTF EIR edits

Chris Bashaw, Assistant Editor
3:59 pm PST December 29, 2014

The City of Malibu published last week a list of “minor edits” to the final Environmental Impact Report for the proposed Civic Center Wastewater Treatment Facility  (CCWTF) project.


Friday, December 19, 2014

Planning Commission Recommends Sewer Report Approval

http://m.malibutimes.com/news/article_6eb8f0da-862d-11e4-9d75-9fc19fbcf11d.html?mode=jqm

Planning Commission Recommends Sewer Report Approval


Commissioners voted 4-0 to recommend approval of project’s environmental report, with further disclosures over soil samples.

Sunday, December 14, 2014

Enviromentalists Go To Battle Over Facewash

http://time.com/3628392/microbead-ban-states/

Environmentalists are hoping a landmark report about how much plastic is in the world's oceans will help get bans on small plastics passed

Civic Center Sewer Project Timeline Granted Extension - News - The Malibu Times

Civic Center Sewer Project Timeline Granted Extension - News - The Malibu Times

Posted 
The city’s petition to grant a 2-year extension on to the Civic Center Wastewater Project was approved unanimously by the L.A. Regional Water Quality Control Board, City Councilmembers said at Monday’s City Council meeting.

Originally scheduled for a 2015 completion, the first phase of sewer construction now has until June 2017 for completion, meaning the city has additional time to gather funds, draw up plans and construct the infrastructure.

This also opens up the possibility for the Serra Canyon neighborhood to eventually opt out of the sewer, since they now have additional years to conduct soil and water tests as a way to prove they should not be obligated to hook up.